19 January 2022

General construction work at the Titan-Polymer, LLC site is 80% complete

It was announced by General Director of the plant Herman Petrushko.

“2021 was quite a busy year. We are working faster. Engineering networks are underway at the moment and the production workshop is almost finished. The workers are setting up the equipment. I think we will continue to work the same way and start the plant up in 2022,” he said.

Head of the plant noted that general construction work was 80% complete and 75-80% of the equipment was assembled, 75% of the infrastructure was ready. Today, more than 7.5 bln rubbles have already been invested in the construction of the plant.

Increase in prices for metal products, electric products and related works has noticeably affected construction dynamics.

General Director of the plant added that the pandemic had not affected the supply of equipment from abroad. Foreign equipment was supplied as scheduled and placed in storage facilities due to timely payments under contracts.

Back  

Thanks for subscribing

Произошла ошибка

Thank you!

We’ll get in touch with you in the nearest time.

Спасибо!

Мы получили ваш вопрос и обязательно ответим вам на почту

Спасибо!

Мы получили вашу заявку и обязательно свяжемся с вами

Callback request

Personal Data Policy

Certificate request

Personal Data Policy

Personal Data Policy

Send your CV

Personal Data Policy

Send your CV

Personal Data Policy

Become investor

Personal Data Policy

Стать волонтером

Personal Data Policy

Задать вопрос

Personal Data Policy

Оставить заявку

Пол

Образование

Желаемая должность

Personal Data Policy